The KAFRIL group References

Tunnelling in Magdeburg

KAFRIL working at Leipzig/Halle Airport

WITRON Expansion Plant II

VGP Park Hall

New construction of press shop

New construction of MFH Robert-Blum-Str.

New construction of MFH Littstr.

Accumotive Kamenz / New construction Plant 2

New hall construction "Dräxlmaier"

Construction of a nursing home with 72 beds

AOC Leipzig

A10 Havelland Highway

A10 Havelland mass demolition bridges
Tunnelling in Magdeburg
VGP Park Hall
CONTRACTOR:
VGP Park Halle S.a.r.l.
ORDER VOLUME:
4,200,000 €
PROJECT DURATION:
2019 - 2021
PROJECT DETAILS:
- 45,000m3 earthmoving in "Cutt&Fill" incl. ground improvement
- 33,000m3 ballast base material supply and installation
- 7000m sewer construction work (STB and KG) up to DN 1400
- 25,000m2 asphalt
New construction of press shop
CONTRACTOR:
Smart Press Shop GmbH & Co.KG
ORDER VOLUME:
6,900,000 €
PROJECT DURATION:
2019 - 2021
PROJECT DETAILS:
- Removal topsoil 58,000 m³
- Slope regulation 110,000 m²
- Soil improvement 85,000 m²
- Construction pit excavation 40,000 m³
- Soil application with delivered soil 55,000 m³
- Road construction incl. asphalt surfaces 16,000 m²
- Fire department bypass, other paved areas 6,500 m²
- Drainage pipes PP DN 100-400; l= 5,200 m
- Drainage pipes StB DN 400-1,500; l= 1,000 m
- Coalescence separator plant
- Throttle structure
- Extinguishing water pipeline 1,300 m; 20 surface hydrants
- .
- Exterior lighting
- Earthworks of all media
- Landscaping
Accumotive Kamenz / New construction Plant 2
CONTRACTOR:
KLEBL GmbH in Neumarkt i.d Opf. Gößweinstraße 2
ORDER VOLUME:
6,000,000 €
PROJECT DURATION:
2017 - 2019
PROJECT DETAILS:
- Earthworks and development work on 18-hectare construction site
- 96,000 m³ earthmoving for excavation pits and foundations etc.
- 164,355 t disposal of earth material up to Z2 according to TR LAGA
- 50,000 m² hydraulic soil consolidation
- 4,170 meters of DN 200 - DN 1400 drainage channels
- 154 drainage shafts DN 1000 - DN 2000
- 16,500 meters of protective pipe systems DN 50 to DN 160
- 56 pieces of cable pull shafts made of StB up to 21 m³ construction volume
- 5 lifting units for wastewater and rainwater systems
- 3 underground rainwater storage basins up to 110 m³ storage volume
- Earthworks and base courses for approx. 52,000 m² hall area
New hall construction "Dräxlmaier"
CONTRACTOR:
GOLDBECK Ost GmbH
ORDER VOLUME:
3,300,000 €
PROJECT DURATION:
2020 - 2021
PROJECT DETAILS:
- 27,000m3 earthmoving in "Cutt&Fill" incl. ground improvement (original ground leveling with a height difference of approx. 3.80m)
- 15.000m3 ballast supporting layer material to be placed
- Sewer construction work up to STB DN 1000
- Construction of the complete outdoor facilities (asphalt and concrete paving)
Construction of a nursing home with 72 beds
AOC Leipzig

CONTRACTOR:
AOC Leipzig Prager Str. GmbH
ORDER VOLUME:
1,950,000 €
PROJECT DURATION:
2019 - 2020
PROJECT DETAILS:
- 30.000m3 excavation of soil / construction waste
- Disposal of 18.000m3 contaminated building rubble
- Demolition of existing cellar vaults up to - 6m below ground level